System Comprises

At Takasago Singapore, we prioritize quality in every project. Our Quality Management System ensures that we meet and exceed industry standards.

Project Support System

Takasago Singapore's project support system is to enhance and deliver reliable quality to our customers

(click on image for full view)

Project Timeline Graph

Inspection

Takasago Singapore utilizes an internal quality control system to maintain high standards throughout project inspections at different stages.

1

Commencement Meeting

Held prior to construction, this meeting identifies potential problems. It confirms the suitability of the design and planning, safety measures, personnel deployment and reviews past successes and setbacks to avoid repeating mistakes. It also establishes the inspection schedule.

2

Progress Inspection

Inspections are conducted during construction to check the integrity of works, including ducts, pipes, thermal insulation, and wiring.

These inspections are to ensure everything is installed properly and may be carried out multiple times as necessary.

3

Completion Inspection

This inspection takes place just before the project is complete.

It evaluates the effectiveness of the installed facilities and checks for any operational issues within the systems.

4

Final Meeting

This inspection takes place just before the project is complete.

It evaluates the effectiveness of the installed facilities and checks for any operational issues within the systems.

Test & Commissioning

An independent in-house team at Takasago Singapore conducts testing and commissioning to ensure customer requirements are met, allowing the project team to focus on delivering quality results.

1

Testing, Measurement and Adjustment

✓ Total Balance of System

✓ Maximum Performance of System & Each Equipment

✓ Performance of Individual item

2

Report T&C results according to T&C standard format

3

Standardize T&C method & result for all project

4

To train on T & C, Technical, Shop Drawing Skills as well as make new communication for T&C member & all staff

5

Final Guarantee of Takasago's Product Quality to customer

Cost Control System

Through its many years of continuous cleanroom projects, Takasago Singapore has the experience and expertise to always offer customers with the most competetive prices. This are acheived throught its design review and project management.

(click on image for full view)

Our Design Review Consists Of:

Design Specifications

Room & Equipment Layout

Materials Used

Market Bench Mark Pricing

Cost Control

Safety Control

In our effort to complete fast paced projects on time, work safety is never forgotten. Takasago views safety as a serious matter and reinforces in-house safety awareness through implementation of the following

SAFETY HANDBOOK

Safety standards compiled from Takasago's safety practices.

SAFETY PATROL

Management takes part in a monthly safety patrol.

SAFETY SUB-CONTRACTOR MEETING

Management of Takasago's sub-contractors takes part in twice yearly meetings to share Takasago and MOM's latest information.

SAFETY IN-HOUSE TRAINING

Yearly safety training that covers not only safety knowledge, but safety-related construction methods and work attitude, as well as methods for constructing project safety systems.

EXTERNAL SAFETY TRAINING

Safety training held at MOM, targeted at all staff.

(Construction Safety Supervisor | Safety Course For Project Manager | Risk Assessment Course)

RISK ASSESMENT

Standardize risk assessment methods accumulated from experience and to turn them toward each site's development.

Sub-Contractors

The subcontractors who support Takasago Singapore not only have a long track record in quality cleanroom construction, but are thorough in safety management and following cleanroom protocol. Takasago Singapore has a control system that assesses new and existing vendor's capability and ensures that approved vendor maintains the required standard.

VENDOR PRE-QUALIFICATION

Submit Vendor Pre-Qualification for management approval.

APPROVED VENDOR LIST

Management takes part in a monthly safety patrol.

YEARLY EVALUATIONS OF VENDOR'S PERFORMANCE

Evaluate Approved Vendor's performance yearly.

BLOCK LISTED VENDOR

Under performing vendors are place in the Black-listed Vendor List.